Q1Resource·Planning
RACI is a type of:
Q2Procurement·Monitoring & Controlling
Procurement audits occur during:
Q3Integration·Executing
In adaptive (agile) approaches, scope is:
Q4Resource·Planning
Resource histogram shows:
Q5Resource·Monitoring & Controlling
Control Resources focuses on:
Q6Integration·Initiating
Assumption log is first created during:
Q7Procurement·Planning
Time & Materials contracts are typically used for:
Q8Communications·Executing
Pull communication includes:
Q9Stakeholder·Planning
Power/Interest grid is used to:
Q10Communications·Executing
Information radiator is a:
Q11Resource·Executing
Best conflict resolution technique long-term:
Q12Integration·Executing
Direct and Manage Project Work produces:
Q13Quality·Planning
Quality is:
Q14Stakeholder·Planning
Value delivery system in PMBOK 7/8 emphasises:
Q15Quality·Planning
Cost of quality includes:
Q16Cost·Monitoring & Controlling
If EV = 400, PV = 500, AC = 450, SPI is:
Q17Cost·Planning
Funding limit reconciliation can cause:
Q18Schedule·Planning
Finish-to-Start with a 3-day lead means:
Q19Integration·Planning
What is the primary output of Develop Project Management Plan?
Q20Scope·Planning
Rolling wave planning is best described as:
Q21Resource·Executing
Tuckman's stages in order are:
Q22Cost·Monitoring & Controlling
EAC assuming future work at the budgeted rate is:
Q23Quality·Executing
Quality audits are performed to:
Q24Resource·Planning
Pre-assignment of resources happens when:
Q25Communications·Planning
Number of communication channels with 10 stakeholders is:
Q26Risk·Planning
Best response to a low-probability low-impact threat with high effort to mitigate:
Q27Resource·Executing
Psychological safety in a team enables:
Q28Scope·Planning
Which document defines acceptance criteria for deliverables?
Q29Communications·Planning
Communication model components include:
Q30Scope·Planning
Requirements traceability matrix links requirements to:
Q31Integration·Monitoring & Controlling
A change request is approved. The next step is to:
Q32Stakeholder·Monitoring & Controlling
Issue log is primarily used to:
Q33Resource·Executing
Servant leadership emphasises:
Q34Risk·Planning
Strategy 'transfer' is for:
Q35Risk·Planning
Expected Monetary Value of a 30% probability, $100k impact risk is:
Q36Procurement·Planning
Cost-Plus-Fixed-Fee places most risk on:
Q37Procurement·Planning
Fixed-Price contract places most risk on:
Q38Cost·Monitoring & Controlling
CPI = 0.85 means:
Q39Procurement·Executing
Source selection criteria are used during:
Q40Risk·Planning
Strategy 'exploit' is for:
Q41Cost·Monitoring & Controlling
Earned Schedule (ES) improves on SPI by:
Q42Quality·Monitoring & Controlling
Pareto chart helps identify:
Q43Quality·Executing
Manage Quality is essentially:
Q44Risk·Planning
Qualitative risk analysis uses:
Q45Schedule·Planning
Schedule compression typically increases:
Q46Integration·Closing
Project closure is considered complete when:
Q47Procurement·Planning
RFP, RFQ, RFI differ primarily in:
Q48Schedule·Planning
Resource levelling often:
Q49Communications·Planning
Adding 2 stakeholders to a team of 8 increases channels by:
Q50Stakeholder·Planning
Negative stakeholders should be:
Q51Integration·Executing
A team member proposes a scope change that adds value. What should the PM do first?
Q52Risk·Planning
A residual risk is:
Q53Communications·Planning
Most reliable communication for resolving conflict:
Q54Cost·Planning
Parametric estimating uses:
Q55Risk·Planning
Tailoring in PMBOK 7/8 means:
Q56Cost·Monitoring & Controlling
VAC is calculated as:
Q57Risk·Planning
Risk register is first produced during:
Q58Integration·Closing
Which is a key activity during Close Project or Phase?
Q59Quality·Planning
Definition of Done in adaptive projects is:
Q60Stakeholder·Monitoring & Controlling
Stakeholder engagement assessment matrix maps:
Q61Communications·Monitoring & Controlling
Monitor Communications output is:
Q62Stakeholder·Planning
Salience model classifies stakeholders by:
Q63Integration·Closing
Final report typically excludes:
Q64Scope·Monitoring & Controlling
Validate Scope focuses on:
Q65Integration·Initiating
Which document formally authorises the project and gives the PM authority to apply resources?
Q66Schedule·Planning
PERT (three-point) estimate using triangular is:
Q67Schedule·Planning
Total float is:
Q68Stakeholder·Initiating
Stakeholder register is produced during:
Q69Resource·Executing
A halo effect is:
Q70Quality·Monitoring & Controlling
Control chart rule: 7 consecutive points on one side of the mean indicates:
Q71Cost·Planning
Contingency reserves are for:
Q72Scope·Monitoring & Controlling
Customer rejects a deliverable in Validate Scope. PM should:
Q73Integration·Executing
Which tool helps capture knowledge across the project lifecycle?
Q74Schedule·Planning
Crashing involves:
Q75Risk·Planning
Risk appetite refers to:
Q76Schedule·Planning
Fast tracking is:
Q77Communications·Executing
55% of communication is reportedly:
Q78Cost·Planning
Analogous estimating is:
Q79Procurement·Planning
Point of Total Assumption applies to:
Q80Risk·Monitoring & Controlling
Risk reassessment occurs during:
Q81Stakeholder·Initiating
Most important reason to identify stakeholders early:
Q82Schedule·Planning
A milestone has:
Q83Scope·Monitoring & Controlling
Control Scope is primarily about:
Q84Quality·Planning
Ishikawa diagram is also known as:
Q85Schedule·Planning
In agile, velocity is used to:
Q86Scope·Planning
Which is NOT part of the scope baseline?
Q87Procurement·Executing
Bidder conference is conducted to:
Q88Stakeholder·Executing
Manage Stakeholder Engagement focuses on:
Q89Schedule·Planning
Free float is:
Q90Integration·Planning
The benefits management plan describes:
Q91Risk·Planning
Sensitivity analysis is typically shown with:
Q92Communications·Executing
Push communication includes:
Q93Integration·Monitoring & Controlling
Work performance information differs from work performance data because it is:
Q94Cost·Planning
Cost baseline is:
Q95Integration·Monitoring & Controlling
Perform Integrated Change Control is primarily concerned with:
Q96Risk·Planning
Risk threshold is:
Q97Scope·Planning
Gold plating refers to:
Q98Scope·Planning
Which technique helps elicit requirements through structured group sessions?
Q99Cost·Monitoring & Controlling
TCPI based on BAC equals:
Q100Schedule·Monitoring & Controlling
Best technique to forecast finish date probabilistically:
Q101Scope·Planning
The WBS decomposes work down to:
Q102Quality·Monitoring & Controlling
Control Quality is essentially:
Q103Schedule·Planning
Critical path is:
Q104Risk·Planning
A secondary risk is:
Q105Schedule·Monitoring & Controlling
SV is negative and SPI < 1. The project is: