Calculators · 12 tools

Working construction PM calculators

All 12 tools run in your browser. No signup, no email wall, no data leaves your device.

Earned Value

Inline tool

CPI Calculator

Cost Performance Index — EV / AC.

CPI
0.90
Over budget
Inline tool

SPI Calculator

Schedule Performance Index — EV / PV.

SPI
0.90
Behind schedule
Inline tool

EAC Calculator

Estimate at Completion — BAC / CPI.

EAC
1,155,556
CPI = 0.87 · VAC = -155,556
Inline tool

TCPI Calculator

To-Complete Performance Index — (BAC − EV) / (BAC − AC).

TCPI
1.15
Unlikely — re-baseline candidate

Risk

Inline tool

Risk Exposure Calculator

Probability × Impact × cost-at-risk.

Risk exposure
80,000
Add to contingency reserve
Inline tool

Contingency Calculator

Risk-weighted contingency reserve from your register.

Contingency reserve
255,000
10.2% of base

Productivity

Inline tool

Productivity Calculator

Output / labour hours with target gap.

Actual rate
5.25 u/hr
Gap vs target: -12.5%
Inline tool

Resource Utilization Calculator

Productive hours / available hours × 100.

Resource utilisation
85.0%
Healthy band: 75–90%

Procurement

Inline tool

Procurement Savings Calculator

Baseline price vs negotiated price savings %.

Savings
16,000
13.3% vs baseline

Cost

Inline tool

Variation Impact Calculator

Cumulative variation impact on cost, time and margin.

Total contract
3,745,000
Scope creep: 7.0% · Indicative margin pressure: 4.9k