A calculator answers a bounded question. An assessment scores a whole position, interprets it against bands, and tells you what to do next. Everything runs in your browser.

Assessment context
71.77READINESS
SIGNIFICANT GAPS71.77
READY TO CLOSE
90100
NEARLY READY
7589
SIGNIFICANT GAPS
5574
NOT READY
054
Points lost
28.23
out of 100 available
Biggest drag
Defects position
−4.35 points
Categories below 75
8
of 12 categories
To reach next band
3.23
points to NEARLY READY
Weighted contribution
Commissioning (verified)11.70
Defects position10.65
Statutory certificates10.20
Final account agreement7.68
As-built documentation9.20
O&M manuals5.36
Asset data & CMMS4.40
Training delivered4.38
Warranties secured4.00
Handover transfers2.40
Outstanding works1.50
Lessons learned embedded0.30
Shortfall28.23
Gate thresholds
C2 Practical Completion
Requires 85 or above
✕ 13.2 SHORT

Zero Category A defects open AND all occupancy certificates issued

C3 Documentation & Handover
Requires 90 or above
✕ 18.2 SHORT

FM written acceptance of O&M and asset data

C5 Final Completion
Requires 97 or above
✕ 25.2 SHORT

All defects closed and verified; outstanding works complete

C6 Commercial & Corporate Close
Requires 100 or above
✕ 28.2 SHORT

Final account signed; retentions released; lessons embedded

Score each category · 0–100
Commissioning (verified)15%

Verified Cx items, weighted to handover-critical systems

11.70 / 15
weighted
NEARLY READY
3.30 pts
Defects position15%

Cat A open, closure rate, aging profile

10.65 / 15
weighted
SIGNIFICANT GAPS
4.35 pts
Statutory certificates12%

Issued vs required; occupancy-gating weighted double

10.20 / 12
weighted
NEARLY READY
1.80 pts
Final account agreement12%

Agreed lines and agreed value vs claimed

7.68 / 12
weighted
SIGNIFICANT GAPS
4.32 pts
As-built documentation10%

Approved and issued vs required

9.20 / 10
weighted
READY TO CLOSE
0.80 pts
O&M manuals8%

FM-accepted volumes vs required

5.36 / 8
weighted
SIGNIFICANT GAPS
2.64 pts
Asset data & CMMS8%

Loaded AND FM-validated

4.40 / 8
weighted
SIGNIFICANT GAPS
3.60 pts
Training delivered6%

Delivered with attendance evidence

4.38 / 6
weighted
SIGNIFICANT GAPS
1.62 pts
Warranties secured5%

Executed with start date recorded

4.00 / 5
weighted
NEARLY READY
1.00 pts
Handover transfers4%

Signed receipts vs required items

2.40 / 4
weighted
SIGNIFICANT GAPS
1.60 pts
Outstanding works3%

Complete vs agreed, value-weighted

1.50 / 3
weighted
NOT READY
1.50 pts
Lessons learned embedded2%

Actions closed vs raised

0.30 / 2
weighted
NOT READY
1.70 pts
Weakest areas

Ranked by points lost, not by raw score

A 62 on a 20%-weighted category costs more than a 54 on a 10% one — weight decides where the effort goes.

  1. 1
    Defects position
    score 71 · weight 15%
    4.35
    SIGNIFICANT GAPS
  2. 2
    Final account agreement
    score 64 · weight 12%
    4.32
    SIGNIFICANT GAPS
  3. 3
    Asset data & CMMS
    score 55 · weight 8%
    3.60
    SIGNIFICANT GAPS
  4. 4
    Commissioning (verified)
    score 78 · weight 15%
    3.30
    NEARLY READY
Generated recommendations

12 actions from this scoring

Defects positionMEDIUM
SIGNIFICANT GAPS — 71/100

Split claimed-complete from verified-complete in the register. The gap between the two, not the raw open count, is what will surface at the final inspection.

Weight 15% · costing 4.3 points · act this month
Final account agreementMEDIUM
SIGNIFICANT GAPS — 64/100

Work the largest unresolved lines first — value, not line count, is what settles the account. Confirm every claim carries the substantiation the contract requires before assessing it.

Weight 12% · costing 4.3 points · act this month
Asset data & CMMSMEDIUM
SIGNIFICANT GAPS — 55/100

Loading is not validating. Have FM validate a sampled subset — minimum 10% or 50 assets — before this counts as complete.

Weight 8% · costing 3.6 points · act this month
Commissioning (verified)LOW
NEARLY READY — 78/100

Close out the remaining witnessed tests and seasonal commissioning. Confirm every handover-critical system holds a signed certificate with recorded readings, not just a pass mark.

Weight 15% · costing 3.3 points · act this month
O&M manualsMEDIUM
SIGNIFICANT GAPS — 67/100

Track by volume and section with draft, comment and acceptance dates. 'No comment received' is not acceptance — chase written FM acceptance explicitly.

Weight 8% · costing 2.6 points · monitor
Statutory certificatesLOW
NEARLY READY — 85/100

Close out attached conditions, not just issued certificates. A certificate with open conditions is a liability sitting in the client's file.

Weight 12% · costing 1.8 points · monitor
Lessons learned embeddedHIGH
NOT READY — 15/100

Nothing is being captured and the team is about to disperse. Book the workshop this month — after demobilisation the knowledge is unrecoverable at any price.

Weight 2% · costing 1.7 points · monitor
Training deliveredMEDIUM
SIGNIFICANT GAPS — 73/100

Schedule the remaining sessions and require signed attendance sheets. A calendar invite is not evidence that training occurred.

Weight 6% · costing 1.6 points · monitor
Handover transfersMEDIUM
SIGNIFICANT GAPS — 60/100

Work the physical category first: keys, access system administration, security codes, spares and attic stock. These are the items that surface as disputes months later.

Weight 4% · costing 1.6 points · monitor
Outstanding worksHIGH
NOT READY — 50/100

Works agreed incomplete at PC are drifting. Every entry needs a value withheld and an agreed completion date — without both it is not a managed deferral, it is an unclosed scope gap.

Weight 3% · costing 1.5 points · monitor
Warranties securedLOW
NEARLY READY — 80/100

Complete the transfer to the client and confirm the beneficiary named on each document is correct.

Weight 5% · costing 1.0 points · monitor
Cross-cuttingHIGH
Knowledge is about to walk out the door

Lessons learned is the first deliverable dropped and the only one that pays forward. Book the workshop before demobilisation — this is the cheapest item on the list and the only one that cannot be recovered later.

Pattern detected across two or more categories
Calculation

How this score was produced

CategoryScoreWeightWeightedPoints lostStatus
Commissioning (verified)7815%11.703.30 NEARLY READY 78
Defects position7115%10.654.35 SIGNIFICANT GAPS 71
Statutory certificates8512%10.201.80 NEARLY READY 85
Final account agreement6412%7.684.32 SIGNIFICANT GAPS 64
As-built documentation9210%9.200.80 READY TO CLOSE 92
O&M manuals678%5.362.64 SIGNIFICANT GAPS 67
Asset data & CMMS558%4.403.60 SIGNIFICANT GAPS 55
Training delivered736%4.381.62 SIGNIFICANT GAPS 73
Warranties secured805%4.001.00 NEARLY READY 80
Handover transfers604%2.401.60 SIGNIFICANT GAPS 60
Outstanding works503%1.501.50 NOT READY 50
Lessons learned embedded152%0.301.70 NOT READY 15
Total100%71.7728.23

Weighted score = Score × Weight ÷ 100. Final = sum of all weighted scores. Points lost = Weight × (100 − Score) ÷ 100.