Working construction PM calculators
All 12 tools run in your browser. No signup, no email wall, no data leaves your device.
Project duration
49 days
Critical path
A → B → C → E → F → G → H
| ID | Activity | Duration | Predecessors | ES | EF | LS | LF | Float | |
|---|---|---|---|---|---|---|---|---|---|
| 0 | 3 | 0 | 3 | 0 | |||||
| 3 | 8 | 3 | 8 | 0 | |||||
| 8 | 15 | 8 | 15 | 0 | |||||
| 8 | 12 | 11 | 15 | 3 | |||||
| 15 | 27 | 15 | 27 | 0 | |||||
| 27 | 35 | 27 | 35 | 0 | |||||
| 35 | 45 | 35 | 45 | 0 | |||||
| 45 | 49 | 45 | 49 | 0 |
Notes: Predecessors are comma-separated activity IDs (e.g. A,B). All relationships are finish-to-start with zero lag. Activities with zero float sit on the critical path and are highlighted.