Calculators · 12 tools

Working construction PM calculators

All 12 tools run in your browser. No signup, no email wall, no data leaves your device.

Line itemBudgetActual to dateForecast at completionVarianceVar %
-1,000-0.8%
-15,000-3.1%
-12,000-5.5%
-8,000-2.6%
-4,000-1.5%
Totals1,390,000828,0001,430,000-40,000-2.9%
How to read it: Positive variance = under budget. Watch the forecast at completion column — it's the early-warning indicator. Update forecasts at every monthly cost report, not just at handover.