Working construction PM calculators
All 12 tools run in your browser. No signup, no email wall, no data leaves your device.
Inputs
Enter the four EVM inputs. Currency unit doesn't matter.
Verdict
Over budget and behind schedule. Escalate.
CPI
0.87
SPI
0.90
TCPI
1.15
VAC
-155,556
| CV — Cost Variance | -70,000 |
| SV — Schedule Variance | -50,000 |
| EAC — Estimate at Completion | 1,155,556 |
| ETC — Estimate to Complete | 635,556 |
Formulas: CV = EV − AC · SV = EV − PV · CPI = EV / AC · SPI = EV / PV · EAC = BAC / CPI · ETC = EAC − AC · VAC = BAC − EAC · TCPI = (BAC − EV) / (BAC − AC)