Working construction PM calculators

All 12 tools run in your browser. No signup, no email wall, no data leaves your device.

Inputs

Enter the four EVM inputs. Currency unit doesn't matter.

Verdict
Over budget and behind schedule. Escalate.
CPI
0.87
SPI
0.90
TCPI
1.15
VAC
-155,556
CV — Cost Variance-70,000
SV — Schedule Variance-50,000
EAC — Estimate at Completion1,155,556
ETC — Estimate to Complete635,556
Formulas: CV = EV − AC · SV = EV − PV · CPI = EV / AC · SPI = EV / PV · EAC = BAC / CPI · ETC = EAC − AC · VAC = BAC − EAC · TCPI = (BAC − EV) / (BAC − AC)